Along the most popular thoroughfares in the core of Scotland's historic capital stands a imposing sight of construction framework.
For the past 60 months, Radisson's G&V Hotel on the junction of a key historic street and the adjacent bridge has been a plastic-wrapped eyesore.
Travellers cannot book rooms, foot traffic are directed through confined passages, and businesses have left the building.
Repair work commenced in 2020 and was originally estimated to last a few months, but now exasperated residents have been told the structure could persist until 2027.
Further Delays
Sir Robert McAlpine (SRM), the lead company, says it will be "close to the conclusion" of 2026 before the first sections of the structure can be taken down.
A local authority figure a city representative has labeled it a "negative feature" on the area, while preservation advocates say the work is "extremely disruptive".
What is happening with this seemingly endless project?
Background Issues
The 136-bedroom hotel was built on the site of the former regional authority offices in 2009.
Estimates from when it initially debuted under the a fashion-branded banner, put the build cost at about thirty million pounds.
Construction activity started soon after the start of the global health crisis with the hotel itself not accepting visitors since 2022.
A lane of traffic and a large section of pavement leading up to the junction of the Royal Mile have been closed off by the project.
People on foot going to and from the a nearby area and another locale have been required in a line into a confined, sheltered corridor.
Seafood restaurant a popular spot departed from the building and moved to another city in 2024.
In a comment, its management said building work had obliged them to modify the restaurant's facade, adding that "guests were entitled to a superior experience".
It is also the location of restaurant chain Pizza Express – which has placed large banners on the scaffold to inform customers it is still open.
Slipped Schedules
An report to the council's transport and environment committee in the start of the year indicated that the process of "exposing" the frontage would commence in February, with a total takedown by the close of the year.
But the firm has said that is incorrect, pointing to "extremely complex" building problems for the postponement.
"We project starting to dismantle parts of the structure near the finish of next year, with subsequent enhancements continuing thereafter," the company commented.
"We are collaborating closely with the relevant stakeholders to ensure we deliver an improved site for the community."
Local and Conservation Frustration
A conservation official, head of heritage body the Cockburn Association, said the work had added to the city's reputation of being "leisurely" for construction projects.
She said those working on the project had a "civic responsibility" to reduce inconvenience and should integrate the work into the city's streetscape.
She said: "It causes the pedestrian experience in that section really difficult.
"It is perplexing why there is not an effort to bring it into the urban landscape or produce something more creative and cutting-edge."
Ongoing Efforts
A project spokesperson said work on "ideas to enhance the appearance the site" was continuing.
They stated: "We recognize the irritations felt by the community and enterprises.
"This represents a long and drawn-out process, highlighting the complexity and magnitude of the remedial work required, however we are dedicated to completing this essential work as soon as is practicable."
The official said the council would "keep applying pressure" on those involved to wrap up the project.
She said: "This framework has been a blight for years, and I share the annoyance of inhabitants and nearby shops over these persistent hold-ups.
"Nonetheless, I also recognize that the company has a obligation to make the building secure and that this restoration has proved to be exceptionally difficult."